Progress of work in the ooranis as on 31 July, 2007

Home >> Ooranis work status

Summary of the Oorani Project for the year July 2006 to July 2007
No. of Ooranis Supported : 14
No. of Ooranis Completed : 1
No. of Ooranis that will be Completed in August 2007 : 8
No. of Ooranis that will be Completed in September 2007 : 3
No. of Ooranis that will be Completed in May 2008 : 2
Community contribution : Rs. 8,04,818
Donor contribution : Rs. 24,85,350
Total Project cost : Rs. 32,90,168
Value of works done so far : Rs. 15,43,952

S.No

Name of the Oorani/Village

Status of work

Value of works done

Project Cost

Community Contribution

Donors Contribution

Completion Date

Works completed
1 Viyasapuram Completed 2,70,000 2,70,000 67,500 2,02,500 Feb 2007
Physical works in progress
2 Thozhupethanendal The earth work has been completed for the creation of the new oorani.The work of inlet construction, steps, fencing etc are in progress 1,04,050 1,90,000 47,500 1,42,500 Aug 2007
3 N. Pethanenthal The earth work has been completed for the creation of the new oorani.The work of inlet construction, steps, fencing etc are in progress 1,22,750 2,50,000 62,500 1,87,500 Aug 2007
4 Salur Fencing work in progress. Earthwork completed last year itself. 1,42,000 2,49,368 49,368 2,00,000 Aug 2007
5 Ulaiyur Nadukudierupppu Earthwork Completed for this oorani. Inlet construction and fencing work is in progress 1,53,130 2,50,000 62,500 1,87,500 Aug 2007
6 Neerkundram Earthwork completed for this oorani. Inlet construction and fencing work in progress. The water in the oorani is currently being used by the community for drinking water. 1,60,000 2,50,000 62,500 1,87,500 Aug 2007
7 Athanakuruchi Construction were completed. Fencing work is in progress 1,80,000 2,67,000 66,750 2,00,250 Aug 2007
8 Nediyamanickam Construction and fencing work in progress. Since the oorani is located inside the tank, the community is mobilising additional funds to create a bund to reach the oorani when the tank is full of water in the peak monsoon period. 1,93,438 2,00,000 50,000 1,50,000 Aug 2007
9 Parukkaikudi Inlet and steps construction and fencing in progress 2,18,584 3,39,000 80,000 2,59,000 Aug 2007
Physical works to be initiated
10 Andichiyenthal The work will begin in January. The community has completed the work of identifying and purchasing a plot of land for the creation of the new oorani. The contribution for the purchase of the land is in addition to the contribution of 25% of the cost of the oorani project _ 2,00,000 50,000 1,50,000 May 2008
11 Kodarendal The community contribution has been mobilised and the work will be initiated in the second week of August. _ 2,00,000 50,000 1,50,000 Sep 2007.
12 Neerkoliyenthal Village association formation and mobilisation of community contribution work in progress. Work on the oorani will begin the second week of August. _ 2,00,000 50,000 1,50,000 Sep 2007
13 Kamalapuram The work of community mobilisation and collection of community contribution is in progress and the work will begin in the middle of August. _ 1,44,800 36,200 1,08,600 Sep 2007
14 Samipatti Community mobilisation work is in progress. The work will be initiated during the second week of August. _ 2,80,000 70,000 2,10,000 Mar 2008
Total 15,43,952 32,90,168 8,04,818 24,85,350

You can also do it….

To help save the lives of the Life saving Ooranis
Kind hearted well-wishers
Can sponsor an Oorani