Progress of work in the ooranis as on 31 July, 2007
Home >> Ooranis work status
| Summary of the Oorani Project for the year July 2006 to July 2007 |
| No. of Ooranis Supported |
: |
14 |
| No. of Ooranis Completed |
: |
1 |
| No. of Ooranis that will be Completed in August 2007 |
: |
8 |
| No. of Ooranis that will be Completed in September 2007 |
: |
3 |
| No. of Ooranis that will be Completed in May 2008 |
: |
2 |
| Community contribution |
: |
Rs. 8,04,818 |
| Donor contribution |
: |
Rs. 24,85,350 |
| Total Project cost |
: |
Rs. 32,90,168 |
| Value of works done so far |
: |
Rs. 15,43,952 |
S.No |
Name of the Oorani/Village |
Status of work |
Value of works done |
Project Cost |
Community Contribution |
Donors Contribution |
Completion Date |
| Works completed |
| 1 |
Viyasapuram |
Completed |
2,70,000 |
2,70,000 |
67,500 |
2,02,500 |
Feb 2007 |
| Physical works in progress |
| 2 |
Thozhupethanendal |
The earth work has been completed for the creation of the new oorani.The work of inlet construction, steps, fencing etc are in progress |
1,04,050 |
1,90,000 |
47,500 |
1,42,500 |
Aug 2007 |
| 3 |
N. Pethanenthal |
The earth work has been completed for the creation of the new oorani.The work of inlet construction, steps, fencing etc are in progress |
1,22,750 |
2,50,000 |
62,500 |
1,87,500 |
Aug 2007 |
| 4 |
Salur |
Fencing work in progress. Earthwork completed last year itself. |
1,42,000 |
2,49,368 |
49,368 |
2,00,000 |
Aug 2007 |
| 5 |
Ulaiyur Nadukudierupppu |
Earthwork Completed for this oorani. Inlet construction and fencing work is in progress |
1,53,130 |
2,50,000 |
62,500 |
1,87,500 |
Aug 2007 |
| 6 |
Neerkundram |
Earthwork completed for this oorani. Inlet construction and fencing work in progress. The water in the oorani is currently being used by the community for drinking water. |
1,60,000 |
2,50,000 |
62,500 |
1,87,500 |
Aug 2007 |
| 7 |
Athanakuruchi |
Construction were completed. Fencing work is in progress |
1,80,000 |
2,67,000 |
66,750 |
2,00,250 |
Aug 2007 |
| 8 |
Nediyamanickam |
Construction and fencing work in progress. Since the oorani is located inside the tank, the community is mobilising additional funds to create a bund to reach the oorani when the tank is full of water in the peak monsoon period.
|
1,93,438 |
2,00,000 |
50,000 |
1,50,000 |
Aug 2007 |
| 9 |
Parukkaikudi |
Inlet and steps construction and fencing in progress |
2,18,584 |
3,39,000 |
80,000 |
2,59,000 |
Aug 2007 |
| Physical works to be initiated |
| 10 |
Andichiyenthal |
The work will begin in January. The community has completed the work of identifying and purchasing a plot of land for the creation of the new oorani. The contribution for the purchase of the land is in addition to the contribution of 25% of the cost of the oorani project |
_ |
2,00,000 |
50,000 |
1,50,000 |
May 2008 |
| 11 |
Kodarendal |
The community contribution has been mobilised and the work will be initiated in the second week of August. |
_ |
2,00,000 |
50,000 |
1,50,000 |
Sep 2007. |
| 12 |
Neerkoliyenthal |
Village association formation and mobilisation of community contribution work in progress. Work on the oorani will begin the second week of August. |
_ |
2,00,000 |
50,000 |
1,50,000 |
Sep 2007 |
| 13 |
Kamalapuram |
The work of community mobilisation and collection of community contribution is in progress and the work will begin in the middle of August. |
_ |
1,44,800 |
36,200 |
1,08,600 |
Sep 2007 |
| 14 |
Samipatti |
Community mobilisation work is in progress. The work will be initiated during the second week of August. |
_ |
2,80,000 |
70,000 |
2,10,000 |
Mar 2008 |
| Total |
15,43,952 |
32,90,168 |
8,04,818 |
24,85,350 |
|